Commission a factory

Goal: take an empty (or partly set up) EightyOne company to a working factory setup, in one reviewed change.

Before you start

  1. Check where you are. Call me_get: check the company and that the user can manage what you'll set up. Then call config_export. An empty factory has a few defaults (its own client, an administrator group); anything else means someone has started. Ask before replacing their work.

  2. Read guide_get topic commissioning, and topic company (the company's own guidance, if any).

  3. Gather the facts from the user, or from documents they give you:

    • areas (floors, cells) and the machines in each, as a tree: a line with its machines;
    • work centers: groups of machines that can run the same operations;
    • products, by SKU: what's bought (with vendors), what's made (with its recipe), units, lot or serial tracking;
    • operations: the task types, the checks each records (its form), standard setup and run minutes;
    • routings: the steps each product goes through, and which steps gate the next ones;
    • machine statuses and downtime and failure reason codes;
    • roles and what each may do (permission groups), teams and skills.

    Never ask about prices or costs.

Build the spec

Everything refers to everything else by name, so keep the names consistent:

Thing Referred to by
machine (SSU) its path: "Site / Line / Machine"
storage unit "Site or warehouse / Unit"
product its SKU (capitals don't matter)
task type, routing, work center, status, role, team, skill, permission group its name
person their email (existing users only)

What the system checks, so get it right the first time:

Review with the user

  1. config_validate, and fix every problem.
  2. config_plan. Summarize it per section: how many creates and updates, and the notable ones.
  3. Call out:
    • anything that changes existing data (update), field by field;
    • permission changes: groups' permissions, roles' groups, people's roles;
    • routings and parameter sets that will release a new version;
    • anything blocked (the user lacks the permission: they need someone who has it);
    • extra items, which are in the company but not in the spec. They're left alone.
  4. Wait for an explicit go-ahead. Then call config_apply with the same spec.

Large specs: go in stages

A whole factory is tens of kilobytes; don't pass it in one call. Split it into these stages and do them in order. Each stage only names what the earlier stages created, so each one validates on its own:

Stage Sections
1. Plant ssuStatuses, reasonCodes, workCenters, sites, warehouses, settings (without the task-type settings)
2. Supply productCategories, vendors, products (large: split it by category if needed)
3. Organisation permissionGroups, roles, teams, skills
4. Work parameterSets, taskTypes, routings, then settings with ncrTaskType and the like
5. Machines and quality machineData, flows, issues, inspectionPlans, guidance
6. People people (only once they've been invited)

Before the first stage, tell the user what the whole template will set up: counts per section and anything unusual. Get the go-ahead for the plan as a whole. Then for each stage, config_plan and check it holds no surprises (a fresh company shows only creates), and config_apply. Stop and ask if a plan shows updates you didn't expect.

Apply and verify

Leave for the user

A spec can't do these; list them at the end: